| TABLE 3. Foundation | ||||||||
| Option A - Raised slab foundation. | ||||||||
| 4" Slab x 11'-3" x 16' / 12 in/ft /27 cubic feet per cubic yard | ||||||||
| 2.222 | Cu. Yd. | |||||||
| Reinforced Footing approximately 1'x1.25'x(2x16+2x9.25) / 27 cubic feet per cubic yard | ||||||||
| 2.337963 | Cu. Yd. | |||||||
| Qty. | Unit | Description | Cost | Total | Comments | |||
| 4.5 | Cu. Yd. | Concrete | $ 65.00 | $ 292.50 | ||||
| 2 | ea. | 2x12x12 | $ 15.00 | $ 30.00 | For Framing - re-use for benches or shelves. | |||
| 2 | ea. | 2x12x16 | $ 20.00 | $ 40.00 | For Framing - re-use for benches or shelves. | |||
| 26 | ea. | Anchor Bolts | $ 2.00 | $ 52.00 | ||||
| 6 | ea. | #4 Rebar (2O ft long) | $ 2.00 | $ 12.00 | ||||
| 1 | Roll | Wire | $ 2.00 | $ 2.00 | ||||
| 1 | Roll | Re-inforcing wire | ||||||
| 1 | Roll | Poly-ethylene | ||||||
| Cu. Yd. | Fill dirt or crushed rock | |||||||
| Total | $ 428.50 | |||||||